IMPLEMENTATION STAGES OF THE MUNICIPAL WASTE

THERMAL TREATMENT PLANT (EfWP) IN POZNAŃ

 

8 IV 2013

Signing of the Public-Private Partnership (PPP) agreement between the city of Poznań
and SITA Zielona Energia

17 X 2013

Obtaining the revised Environmental Decision

18 XI 2013

Obtaining the revised Location Decision

6 II 2014

Obtaining the final construction permits

18 IV 2014

Commencement of construction works

22 V 2014

The official ceremony of the "First Shovel"
for the construction of the EfWP

IX 2014

Commencement of the waste bunker construction and the “emergence" of the first installation wall above the surface of the ground

V-X 2015

Installation of technological equipment (including boiler, grate, fume treatment system, installation of the slag adjustment and turbine with a generator)

III-X 2016

start-up of the installation

XI 2016

Putting the installation into use
(43 months from the signing of the agreement)

2041

The EfWP shall be transferred to the city of Poznań
(termination of the PPP agreement after 25 years
from the launch of the installation)